Where we are now - Background to the Project - 2006
Christmas 2006
Parents & Teachers reps found for all 4 schools invited to further scrutinse plans at GCC offices
11th Dec 06
Representatives of parents and teachers of all 4 merging schools meet with GCC to be briefed on timescales & were invited by the council to comment on all 6 submissions. Each design submission was annonimised
4th Dec 06
Deadline for tender submission from final 6 architect teams
25th Oct 06
Shortlist of 6 architect selected by GCC
4th Oct 06
Approximately 40 expression of intent received
Sept 2006
Advert placed by the council in the OJEU - Click here to view
12th April 06
Deadline for parents to comment of the proposals for catchments areas
23rd Feb 06
Glasgow City Council approves the decision of the education committee to change catchments areas for Andeston, Dowanhill, Hillhead, Hyndland, and Kelvinhaugh
2nd Feb 06
Glasgow city council education services committee decision to build a new non-denominational school to replace Downhill, Hillhead, Kelvinhaugh, Willowbank Primaries and Dowanhill & Willow nurseries. The chosen site is Otago Street
2005
9th Dec 05
Deadline for parents to respond to original consultation document
3rd Nov 05
Public meeting at Hillhead Primary School
13th Oct 05
Education Committee agreed to consult a number of proposals. Proposal J affected children currently attending Dowanhill, Hillhead, Kelvinhaugh, Oakgrove, & Willowbank Primary + Dowanhill and & Willows Nurseries
Please see other news from 2007 to 2008