Where we are now - Background to the Project - 2006

Christmas 2006

Parents & Teachers reps found for all 4 schools invited to further scrutinse plans at GCC offices

 

11th Dec 06 

Representatives of parents and teachers of all 4 merging schools meet with GCC to be briefed on timescales & were invited by the council to comment on all 6 submissions. Each design submission was annonimised

 

4th Dec 06  

Deadline for tender submission from final 6 architect teams   

 

25th Oct 06  

Shortlist of 6 architect selected by GCC

 

4th Oct 06  

Approximately 40 expression of intent received  

 

Sept 2006

Advert placed by the council in the OJEU - Click here to view

 

12th April 06  

Deadline for parents to comment of the proposals for catchments areas

 

23rd Feb 06 

Glasgow City Council approves the decision of the education committee to change catchments areas for Andeston, Dowanhill, Hillhead, Hyndland, and Kelvinhaugh

 

2nd Feb 06

Glasgow city council education services committee decision to build a new non-denominational school to replace Downhill, Hillhead, Kelvinhaugh, Willowbank Primaries and Dowanhill & Willow nurseries. The chosen site is Otago Street


2005

 

9th Dec 05

Deadline for parents to respond to original consultation document

 

3rd Nov 05  

Public meeting at Hillhead Primary School

 

13th Oct 05 

Education Committee agreed to consult a number of proposals. Proposal J affected children currently attending Dowanhill, Hillhead, Kelvinhaugh, Oakgrove, & Willowbank Primary + Dowanhill and & Willows Nurseries


Please see other news from 2007 to 2008

 